i. For any solar PV projects approved before July 1, 2011 and put into operation by December 31, 2011, but without NDRC’s review and approval for pricing, the feed-in tariff is set at 1.15yuan/kWh (including tax, same applicable to the below).
II. For solar PV projects approved through concessionary bidding, the price that was set in the bidding documents shall apply, and the price will not be higher than the benchmark feed-in tariff for solar PV.
III. For solar PV projects granted by Central Committee’s fiscal subsidies, the tariff applied shall be the same as that for local coal-fired power plants with desulfurization installations.
IV. For the part of the tariff that’s higher than that set for local coal-fired power units with desulfurization installations, practice shall refer to the Renewable Energy Power Generation Pricing and Fees Sharing Management Trial Method(No. 7 [2006] of NDRC), and the difference shall be covered through renewable energy electricity price amendments collected nationwide.